Fayette sewer work update 2013.04.03

Written by David Green.

Fayette Village administrator Steve Blue told village council members last week that the first paving of streets torn up through the sewer project is scheduled in late May or early June.

Blue said he's heard mixed reports from citizens about interaction with Gleason Construction, the firm contracted for the sewer project. Some residents are pleased with the extra concern shown by the company; others have complained about the difficulties brought on by the work. 

"They've been responsive to our requests from the village office," Blue said about Gleason.

CONTAMINATION—In response to continuing concerns about construction near the former Fayette Tubular Products site, Blue reported on the testing of soil from the contaminated area. Soil samples were collected and tested by the Bowsher-Morner engineering firm.

Trace amounts of two chemicals associated with Fayette Tubular were detected in the soil, but the levels were not high enough to pose concern, Blue was told, nor to require special disposal.

Additional work in the area is yet to come, Blue said, and approval has already been given by Camille Ajaka, representing the property owner, and by the Ohio EPA.

Gleason made arrangements with Trevor Hibbard to accept excess dirt from the sewer project, and Hibbard will be notified of the contamination. 

"If he does not want to accept it, then the sledding hill would be the logical method to use [for disposal]," Blue said.

One council member asked if the construction soil was given to Hibbard for free. 

"It costs money to dispose of it, so it shouldn't be considered giving it to him," Blue said. 

Some village residents have requested to have a load of soil taken to their property, he said.

TREE—There's still one tree in need of removal for the sewer project, but a resident continues to park a vehicle under the tree to prevent cutting. Village solicitor Tom Thompson wrote a letter to the property owner in hopes of persuading cooperation, but the resident responded by saying that he would stand underneath the tree if a crew came to remove it.

The tree is in the village right-of-way, Thompson stated, but eminent domain procedures might take too long before the work is needed to be done. To move the sewer line to a new location would cost as much as $10,000. Council agreed to have Thompson begin eminent domain procedures and Gleason will be contacted about how long the company would be able to delay that section of the work.

Council member Julia Ruger said the person is holding firm because he did not like the way the tree-cutting issue was handled initially.

OHIO STREET—Design work is complete for replacement of the Ohio Street water line. Blue said he's waiting for final approval from the Ohio EPA to have the project become part of the sewer project. He credited councilor Dave Wheeler for the idea of approaching the project through the sewer work.

  • Front.tug
    MORENCI pep rallies generally end with a tug of war. The senior class entry, shown above, did not advance to the finals. Griffin Grieder, Alaina Webster, Kyle Long and Jazmin Smith are shown at the front of the rope, giving it their best effort.
  • Accident
    FAYETTE resident Patricia Stambaugh, 64, was declared dead on the scene of a single-vehicle accident Friday morning south of Morenci. Rescue units were called around 9 a.m., but as of Tuesday, law enforcement officers had not yet determined the time of the accident. According to Ohio State Highway Patrol, Stambaugh was driving west on U.S. 20 when her Chevrolet Malibu traveled off the north side of the road and down a steep embankment, coming to rest in Bean Creek (Tiffin River).
  • Athletic Fields
    SPORTS COMPLEX—Fayette’s outdoor athletic facilities will include three ball fields for summer recreation leagues at the southwest corner of the school. The baseball and softball fields, along with the running track, will be constructed on the east side of the school. Outdoor athletic fields were not part of the new school project from 2007, but voters approved a $1.4 million levy for a school addition and the sports fields last August. Both projects are scheduled to be complete by July 20.
  • Front.teacher Leading
    PRESCHOOL MUSIC—Fayette band director Jeffrey Dunford spends the last half hour of the day leading the full-day preschool class in musical activities. Additional photos are on page 7 of this week’s Observer.
  • Front.F.band
    TROMBONISTS Jake Myers (left) and Max Baker perform Friday at the annual Senior Citizens Luncheon at Fayette High School. The National Honor Society and the FFA chapter teamed up to serve a meal to area seniors and to provide musical entertainment. Both the school band and choir performed. Additional photos are on page 7 of this week’s Observer.
  • Station.2
    STRANGE STUFF—Morenci Elementary School students learn that blue isn’t really blue when seen through the right color of lens. Volunteer April Pike presents the lesson to students at one of the many stations brought to the school by the COSI science center. The theme of this year’s visit was the solar system.
  • Front.poles
    MOVING EAST—Utility workers continue their slow progress east along U.S. 20 south of Morenci. New electrical poles are put in place before wiring is moved into place.

Weekly newspaper serving SE Michigan and NW Ohio - State Line Observer ©2006-2017