Vreba-Hoff, DEQ reach settlement 6.13.07

Written by David Green.

By DAVID GREEN

A new waste treatment system, another financial penalty, limits on herd growth, enhanced reporting requirements, eventual closure of the Packard Road satellite lagoon, and the threat of new fines for unlawful discharges—those are among the points listed in a 62-page interim order announced June 6 in a Lansing circuit court.

The Michigan Department of Environmental Quality (DEQ) and Vreba-Hoff Dairy signed a settlement agreement June 6 to end legal action against dairy owners that began in January.

As in past settlements, accepting the document “does not constitute an admission by Vreba-Hoff that the law has been violated.” The DEQ has issued citations for discharges on numerous occasions since the first of two farms opened south of Hudson in 1998.

Vreba-Hoff will pay $180,000 in fines to the State of Michigan for violations and enforcement costs and must have a new waste treatment system in operation by Sept. 15. The new EarthMentor system—expected to cost in excess of $2 million—is described below.

Existing manure lagoons will be converted for use in the new six-step treatment system and additional cells will be constructed. A 30 million gallon, clay-lined treatment cell is under construction at the Vreba-Hoff II farm on U.S.-127 and a 23 million gallon cell is being built at Vreba-Hoff I on Dillon Highway.

Smaller treatment cells and manure processing buildings will also be constructed.

If the dairy company fails to treat manure as specified in the settlement, manure must be removed from the farm or the number of cows must be reduced.

Unlawful discharges will bring fines of up to $10,000 a day, depending on the nature of the discharge.

The satellite lagoon constructed early this year on Packard Road can be used for manure storage either for an additional 32 months or until all manure in the lagoon is treated via the new EarthMentor system.

In January, the DEQ sought a herd reduction of 40 percent, but through a mediation process, the population of approximately 6,530 cows was to be reduced to 6,266. This figure was reached before the settlement was announced, according Vreba-Hoff attorney Jack Van Kley.

When the Earth Mentor system is in operation, the dairy will be able to increase herd size to 6,466. When the primary treatment cell reaches operational capacity and is ready to discharge into the second treatment cell, the herd may be increased by no more than 100 cows a month until a maximum of 7,266 is reached.

Vreba-Hoff must refrain from building any new structures for animals for 10 years.

The dairy is faced with a several guidelines, such as informing the DEQ before land application, observing setbacks along streams, incorporating manure into the soil on the day it is applied, and regulating the amount of untreated manure in storage.

Michigan attorney general Mike Cox stated in a DEQ press release that, “Mega-farms require great regulatory scrutiny because they have the potential to severely impact the environment. The enforcement action taken was a necessary step to compel compliance with our environmental laws and again demonstrates my commitment to preserve and protect our natural resources.”

Tom Menke, a consultant with a new environmental management company, said, “Vreba-Hoff is pleased that all issues have been resolved, and is looking forward to proceeding with exciting new advances in technology.”

Details:

A settlement reached last week with the Michigan DEQ calls for installation of a new treatment system incorporating elements of a typical municipal system, along with enhancements to meet the needs of the dairy. The system is known as the EarthMentor Natural Nutrient Reclamation and Treatment System.

The six-step process is more extensive than many municipal systems, said Vreba-Hoff attorney Jack Van Kley, and it’s new for dairies to use this approach.

1. The first step, Van Kley said, is to install sand separation units at both farms to remove sand from manure. The sand is used as bedding in the barns.

The cyclone sand separation system creates a vortex inside a tank, explained Mark Knoblauch of Morenci, who serves as an environmental consultant to Vreba-Hoff. Knoblauch operated the City of Hudson’s wastewater treatment system for many years.

Between 75 and 80 percent of the sand will settle out, Knoblauch said, which will be composted to kill off pathogens.

2. Manure is then run through a system to begin separating solids from liquids. The solids could be run through the existing press system that Knoblauch has made operational or they could be composted without the press system.  Van Kley said the press system will be shut down when the new one is operational. After composting, the solids will be applied on fields.

3. Liquids are directed into the first settling basis for additional separation. Pumps will be used to remove solids.

4. Liquids then move on to a second settling basin to continue the settling process. Existing storage lagoons will be used in the process along with some new construction.

“You’re getting water with less and less manure in it,” Knoblauch said.

5. Anaerobic treatment begins in step 5, incorporating a lagoon holding up to 40 million gallons. The anaerobic process is just like Morenci’s wastewater system, Knoblauch said, where the lack of oxygen kills off pathogens over time.

The liquid will be held here for six months, he said, with additional settling occurring.

6. A holding cell will store the liquid before it’s used for irrigation.

“By the time it makes it to step six, it’s probably clean enough,” Van Kley said, although additional treatment will continue there.

It’s tested technology, Knoblauch said, although it’s not tested on cow manure. While municipal systems discharge into a river, liquid from the Vreba-Hoff system will only be used for field application.

  • Front.splash
    Water Fun—Carter Seitz and Colson Walter take a fast trip along a plastic sliding strip while water from a sprinkler provides the lubrication. The boys took a break from tie-dyeing last week at Morenci’s Summer Recreation Program to cool off in the water.
  • Front.starting
    BIKE-A-THON—Children in Morenci’s Summer Recreation Program brought their bikes last Tuesday to participate in a bike-a-thon. Riders await the start of the event at the elementary school before being led on a course through town by organizer Leonie Leahy.
  • Front.pokemon
    LATEST CRAZE—David Cortes (left) and Ty Kruse, along with Jerred Heselschwerdt (standing), consult their smartphones while engaging in the game of Pokémon Go. The virtual scavenger hunt comes to life when players are in the vicinity of gyms, such as Stair District Library, and PokéStops such as the fire station across the street. The boys had spent time Monday morning searching for Pokémon at Wakefield Park.
  • Front.drum
    on your mark, get set, drum!—Drew Joughin (black shirt), Maddox Joughin and Kaleea Braun took the front row last week when Angela Rettle and assistants led the Stair District Library Summer Reading Program kids in a session of cardio drumming. The sports and healthy living theme continued yesterday with a Mini Jamboree at Lake Hudson State Park arranged by the Michigan Department of Natural Resources. Next week’s program features the Flying Aces Frisbee show.
  • Girls.on.ride
    NADIYA YORK and Aniston Valentine take a spin on the Casino, one of the rides offered at Wakefield Park during Morenci’s Town and Country Festival. This year’s festival remained dry but with plenty of heat during the three-day run. Additional photographs are inside this week’s Observer.
  • Front.softball
    Angela Davis (2) and teammate Allison VanBrandt break into a jig after Morenci's softball team won its third consecutive regional title.
  • Front.art.park
    ART PARK—A design created by Poggemeyer Design Group shows a “pocket art park” in the green space south of the State Line Observer building. The proposal includes a 12-foot sculpture based on a design created by Morenci sixth grade student Klara Wesley through a school and library collaboration. A wooden band shell is located at the back of the lot. The Observer wall would be covered with a synthetic stucco material. City council members are considering ways to fund the estimated $125,000 project and perhaps tackling construction one step at a time.
  • Front.train
    WRECKAGE—Morenci Fire Department member Taylor Schisler walks past the smoking wreckage of a semi-truck tractor on the north side of the Norfolk and Southern Railroad tracks on Ranger Highway. The truck trailer was on the south side of the tracks
  • Funcolor
    LEONIE LEAHY was one of three local hair stylists who volunteered time Friday at the Morenci PTO Fun Night. Her customer, Aubrey Sandusky, looks up at her mother while her hair takes on a perfect match to her outfit. Leahy said she had a great time at the event—nothing but happy clients.
  • KayseInField
    IN THE FIELD—2004 Morenci graduate Kayse Onweller works in a test plot of wheat in Texas. She’s part of Bayer CropScience’s North American wheat breeding program based in Nebraska, where she completed post-graduate work in plant breeding and genetics.

Weekly newspaper serving SE Michigan and NW Ohio - State Line Observer ©2006-2016